Measuring developer productivity? A response to McKinsey
The consultancy giant has devised a methodology they claim can measure software developer productivity. But that measurement comes at a high price – and we offer a more sensible approach. Part 1.
👋 Hi, this is Gergely with the monthly, free issue of the Pragmatic Engineer Newsletter. In every issue, I cover challenges at Big Tech and startups through the lens of engineering managers and senior engineers.
Subscribe to get two full issues every week. Many subscribers expense this newsletter to their learning and development budget. If you have such a budget, here’s an email you could send to your manager.👇
Last week, in The Pulse #59, I asked the question whether measuring developer productivity is going mainstream, after McKinsey had announced entering this space. I wrote:
“Last week, the company published an article titled Yes, you can measure software developer productivity. This article caused quite a stir in the software development community. Kent Beck — software engineer and the creator of extreme programming — wrote that ‘The report is so absurd and naive that it makes no sense to critique it in detail.’ “
While I did not like the direction this report was going, I chose to look at the positive side: how McKinsey getting involved signals there is a growing need even at ‘traditional’ companies to understand more about how software development teams work.
But something felt off. A few hours after publishing this article, I was already on a call with Kent, as we tried to pinpoint exactly why both of us felt frustrated with this report. We almost immediately were on the same page, and figured we can help the software engineering community by putting what we discussed in words. Below is our response, written by myself and
, but with one, shared voice. We are publishing this article in and in — the newsletter written by Kent — simultaneously. Read Kent Beck’s version of this article.What happens when you start to measure things? Kent Beck worked at Facebook for 7 years, and has first-hand experience on a similar situation. As he shared:
“At Facebook we [Kent here] instituted the sorts of surveys McKinsey recommends. That was good for about a year. The surveys provided valuable feedback about the current state of developer sentiment.
Then folks decided that they wanted to make the survey results more legible so they could track trends over time. They computed an overall score from the survey. Very reasonable thing to do. That was good for another year. A 4.5 became a 4. What happened?
Then those scores started cropping up in performance reviews, just as a "and they are doing such a good job that their score is 4.5". That was good for another year.
Then those scores started getting rolled up. A manager’s score was the average of their reports’ scores. A director's score would be the average of their reporting managers’ scores.
Now things started getting unhinged. Directors put pressure on managers for better scores. Managers started negotiating with individual contributors for better survey scores. “Give me a 5 & I’ll make sure you get an ‘exceeds expectations’.” Directors started cutting managers & teams with poor scores, whether those cuts made organizational sense or not.”
Things went from, “we’d like to know how things are going,” to, “we know even less about how things are going. But they are definitely going worse because people are now gaming the system.” How did this occur? Well, because we started to measure & incentivize (with money & status) changes in the measures! And measuring leads to behavior change – behaviour change including coming up with creative ways to improve those measurement scores even at the expense of results that everyone agrees matter.
In this two-part article, we seek to arm engineering leaders with perspectives to the question: Can you measure developer productivity? It’s the sum of our viewpoints, professional experiences, and what we’ve seen work, firsthand:
- brings 40 years of software engineering experience, and has tried, failed, and tried again to measure developer productivity for almost all this time.
- brings 15 years of software engineering experience, including 5 years’ managing engineering teams.
Two weeks ago, McKinsey published the article “Yes, you can measure software developer productivity.” In it, the company claimed it has an approach for measuring software developer productivity that nearly 20 companies already use, and that the consultancy is ready to extend the roll out of the custom approach.
As tempting as it is, we won’t go into a detailed critique of the McKinsey article and the measurement methodology. The thinking that’s evident in the article is absurdly naive and ignores the dynamics of high-performing software engineering teams. But it was written for a reason: CEOs and CFOs are increasingly frustrated by CTOs throwing up their hands and saying software engineering is too nuanced to measure, when sales teams have individual measurements and quotas to hit, as do recruitment teams in the number of positions to fill. The executive reasoning goes: if other groups can measure individual performance, it’s absurd that engineering cannot.
The reality is engineering leaders cannot avoid the question of how to measure developer productivity, today. If they try to, they risk the CEO or CFO turning instead to McKinsey, who will bring their custom framework, deploy it – even as the CTO protests – and start reporting on custom McKinsey metrics like “Developer Velocity Benchmark Index,” “Contribution Analysis,” and “Talent Capability.”
We believe that introducing such a framework is wrong-headed and certain to backfire. The McKinsey framework will most likely do far more harm than good to organizations – and to the engineering culture at companies. Such damage could take years to undo. So let’s get around to answering this question without evasion, and give demanding CEOs and CFOs what they want.
We cover:
A mental model of the software engineering cycle
Where does the need for measuring productivity come from?
How do sales and recruitment measure productivity so accurately?
Measurement tradeoffs in software engineering
And in Part 2, we wrap this topic up with:
The danger of only measuring outcomes and impact
Team vs individual performance
Why does engineering cost so much?
How do you decide how much to invest in engineering?
How do you measure developers?
Who is this article for?
We wrote this article for software developers and engineering leaders, and anybody who cares about nurturing high-performing software development teams. By “high performing” we mean teams where developers satisfy their customers, feel good about coming to work, and don’t feel like they’re constantly measured on senseless metrics which work against building software that solves customers’ problems. Our goal is to help hands-on leaders to make suggestions for measuring without causing harm, and to help software developers become more productive.
When reading articles like McKinsey’s, keep in mind they’re written for a very different, and specific, audience: untechnical CEOs and CFOs with little to zero experience with software development. Engineering is just another department. They need to treat engineering the same way they treat Sales or Recruitment – and will do so, regardless of the damage misconceived frameworks do to development culture.
1. A mental model of the software engineering cycle
Before we jump to our solution, let’s set some context. How does software engineering create value? Take the typical example of building a feature, then launching it to customers, and iterating on it. What does this cycle look like? Say we’re talking about a pretty autonomous and empowered software engineering team working at a startup, who are in tune with customers:
We start by deciding what to do next, and then we do it. This is the effort like planning, coding and so on. Through this effort, we produce tangible things like the feature itself, the code, design documents, etc. These are the output. Customers will behave differently as a result of this output, which is our outcome. For example, thanks to the feature they might get stuck less during the onboarding flow. As a result of this behavior change, we will see value flowing back to us like feedback, revenue, referrals. This is the impact.
So let’s update our mental model with these terms:
The effort-output-outcome-impact model describes software engineering, and works just as well for smaller tasks as it does to model thinking about feature development, or shipping complex projects.
We reference this model throughout this article.
2. Where does the need for measuring productivity come from?
Before we answer how to measure, let’s start with the more important question:
Who wants to measure productivity, and why?
This is such an important question to start with. The answer will differ dramatically, depending on who’s asking, and what the goal of the question is. Here’s a few common examples:
#1: a CTO who wants to identify which engineers to fire. “How can I measure the productivity of engineers in the organization, to identify the least productive 10%, and let them go?”
Unfortunately, this case is timely in the wake of recent layoffs across the tech industry. Here are some ways to answer it:
Identify the lowest performers based on the latest performance review scores. This approach uses historical data that is likely somewhat outdated.
Decide based on tenure, and lay off based on the “last in, first out” method. This uses no performance-related data and simply assumes that the exit of recent joiners will affect productivity less.
Decide on a few easy-to-measure metrics like the number of pull requests, number of tickets closed, and so on. Basically, to decide by effort and output.
Ask managers to identify the number of engineers to be let go. This approach can harness team dynamics and unquantifiable information like a manager knowing which engineers are about to hand in their resignation, which quantitative metrics miss.
With layoffs, team dynamics are impacted, and any approach which fails to take this into account, is likely to result in a less than ideal outcome. At the same time, layoffs often come with constraints, like senior leadership not wanting to get line managers involved. As a result, decisions are often made based on metrics known to be incorrect.
#2: To compare two investment opportunities. “How can I measure the productivity of teams, and allocate additional headcount to the team that will make the most efficient use of additional headcount?”
To answer this question, you want to compare the return on investment. This is not a question about productivity, it’s about the impact of allocating more headcount to one team or another
#3: To manage performance. “How can I measure engineers’ productivity to identify and reward the top 10%, and to identify the bottom quarter in order to debug and improve their performance?”
There are plenty of ways to go about measuring performance, and doing so with metrics is possible, though error prone. A hands-on manager can immediately name their bottom and top performers, and then examine and debug outputs, and look closer at how engineers do their work (their effort.) Performance calibrations are a standard way to do this.
#4: a software engineer who wants to grow at their craft. The question could be: “How can I measure my own productivity, and which metrics can I improve to become a better engineer?” This is a question more engineers should ask of themselves! Here are two helpful approaches:
Aim to only have one red test at a time when using test driven development (TDD). This approach measures both effort and output. Get to the point where you can confidently, deliberately and consistently have one red test, when you expect one red test.
Set a goal to merge a pull request every day, and track this goal over a week. This measure includes both effort and output. This goal forces you to do smaller commits, which are easier to review and get signed off quicker. It also pushes you to write code that’s correct and follows team standards.
As long as you keep tracking these “scores” and work on improving them, you’ll almost certainly improve your efficiency as a software engineer.
But what would happen if you showed these metrics to your manager and your performance was then judged by them? It would be a disaster: you’d be measured not on outcomes or impact, but by output. When you experiment with approaches – for example, learning a new language to help a team in need – then your output could drop, even though you are helping the team achieve a better outcome!
3. Why can sales and recruitment measure productivity so accurately?
As the software engineering industry, we should collectively admit we’ve done a much worse job of measuring productivity down to the individual level, than other functions have. Take sales as an example. Here is Kent’s account of the level of accountability Sales operates at, from a meeting of sales and engineering leadership at one of his past companies:
“I clearly remember this meeting where it was engineering and sales leadership reporting on progress. Each person from the sales team spoke and gave an update which went something like this:
‘My team’s target for the quarter was $600K, and we delivered $520K. I take accountability for the miss. Here are the reasons it happened, and here is my plan of what I’m changing to hit next quarter’s goal of $650K. Additionally, here is a two-quarter-long initiative I am putting in place, which I expect will bring an incremental $100K for each quarter, once complete. Any questions?’
If anyone had questions, the sales leader would drill down all the way to the individual level – which sales reps were above quota and which were below it, and by how much – and do so in a way that everyone in the room understood.
And then, it was engineering’s turn. My goodness, the contrast was stark. The typical engineering update went something like this:
‘So, this quarter we shipped Feature A, and we are slightly behind on some tech debt migration, and next quarter we’ll ship Feature B and catch up on the migration. Any questions?’
If anyone had questions about some delay, the answer was never about individuals – as with sales – and usually included factors like unforeseen difficulties, tech debt, APIs; all things which non-engineers in the room didn’t really understand.”
The level of accountability which sales and customer support work with is on a completely different scale from what a CEO observes from engineering. But when the CEO examines overall departmental costs, engineering probably costs more than sales!
It’s not just sales that demonstrates higher levels of accountability. Recruiting teams have targets for “heads to fill.” A recruitment team can without hesitation answer the question of what percentage of their targets have been met, how many more recruiters they need to meet aggressive hiring targets, and to identify the top and the bottom recruiters, purely based on metrics.
Let’s put ourselves in the shoes of a CEO. Sales has ways to clearly measure productivity, as does recruitment. So why not engineering?
Let’s return to our effort-output-outcome-impact mental model of how software engineering works. We can apply this model to sales and recruitment. The sales team measures itself by deals closed, so where does this metric go in the model? It falls into “outcome” or “impact:”
What about the recruitment team’s main metric: the number of heads filled? It’s also categorized as “impact:”
We can repeat this exercise for other functions with high accountability in how they work. For example, customer support can be measured by the number of tickets closed (an outcome), the time it takes to close a ticket (also an outcome,) and by customer satisfaction scores (impact.)
Neither Kent nor I have seen accountable teams within tech companies which are not measured by outcome and impact. In order to make software engineering more accountable, we need to look at how to do this.
4. Measurement tradeoffs in software engineering
One popular framework to measure software engineering team efficiency is the DORA framework. Let’s map out the focus of this framework measurement:
All DORA metrics measure outcomes or impact.
Let’s look at another way to measure developer productivity: the SPACE framework. It seeks to capture satisfaction, performance, activity, communication, and efficiency (SPACE.) It’s not only outcomes and impact, as with DORA. The SPACE framework does not outline definite metrics – but gives example ones. Several of the metrics come with a warning, like measuring lines of code. Metrics that come with a warning from the SPACE framework authors – such as the ‘lines of code’ metric – tend to measure effort or output.
One critique of McKinsey’s system we have is that nearly every one of its custom metrics which differ from DORA and SPACE metrics, measure effort or output:
What’s wrong with this approach? First, the only folks who care about these metrics are the people collecting them. Customers don’t care. Executives don’t care. Investors don’t care. Second, and most crucially, collecting & evaluating these metrics hinders the measures downstream folks actually do care about, like profitability.
Why is McKinsey adding ways to measure effort? One reason is that it’s the easiest thing to measure! But the McKinsey approach ignores an important truth: the act of measurement changes how developers work, as they try to “game” the system.
The earlier in the cycle you measure, the easier it is to measure. And also the more likely that you introduce unintended consequences. Let’s take the extreme of measuring only profits. The good news is that everyone is aligned, across the company! The bad news: attributing who contributed how much to the profit is nearly impossible! You can ‘fix’ the attribution question by measuring outputs, or effort. But the cost is that you change people’s behavior, as it incentivises them to game the system to ‘score’ better on those metrics:
Let’s take the case of a company that’s reasonably profitable and in the upper quartile for the industry. The company’s leadership dislikes being unable to attribute individuals’ performance in contributing to profitability.
Would you be tempted to screw up your company’s business by introducing micro-measuring? Hell no!
We urge engineering leaders to look to outcome and impact measurements, to identify what to measure. It’s true that it is tempting to measure effort. But there’s a reason why sales and recruitment teams are not judged by their performance in being in the office at 9am sharp, or by the number of emails sent – which are both effort or output.
So which outcomes and impacts can be measured for engineering teams? DORA and SPACE give some pointers, and we offer two more:
Producing at least one customer-facing thing per team, per week. This output might not sound so impressive, but in practice is very hard to achieve. The most productive teams – and nimble companies – can pull this off, though. If you consider why a startup moves so fast and executes so well, it’s because they have to do so out of necessity, even if they do not measure this.
Delivering business impact committed to by the team. There is a good reason why “impact” is so prevalent at the likes of Meta, Uber, and other fast-moving tech companies. By rewarding impact, the business incentivizes software engineers to understand the business, and to prioritize helping it reach its goals. Is shipping a $2M/year cost-saving exercise via a configuration change, less valuable than shipping a $500K/year cost-saving exercise that takes 5 engineering months? No! You don’t want to focus solely on impact, but not focusing on the end goal of delivering business value is a poor choice.
Takeaways
There is, undoubtedly, mounting pressure from the business in wanting to quantify the productivity of software development teams. Companies like McKinsey are responding to this clear demand by providing frameworks that promise to do exactly this.
We don’t think that measuring effort and output is necessarily the answer: as these come with tradeoffs that will negatively impact the engineering culture. As engineering leaders: be sure to consider this tradeoff, and how it could change the incentives of developers.
Part 2 of the article is coming out on Thursday. In the second and final part, we will go into the dangers of only measuring outcomes and impact; and offer our answer to the question on how to measure developer productivity.
Part 2 of the article is where this article diverges from our shared voice to separate ones:
will be giving his candid take on this topic. Sign up to his newsletter: Software Design: Tidy First?As a programming note: expect The Pulse to come out this week; it will just be on Wednesday.
It’s interesting to reflect how how Uber is measuring engineering productivity: given that the ridesharing giant has built a dashboard to visualize statistics that measure output like diff count, reviews per software engineers. These metrics measure output. At the same time, the company also measures things like create to close time, and focus hours per software engineer.
It is likely that Uber considered the impact in change of behaviour after rolling out these metrics: engineers creating smaller diffs, aiming to close these faster, and carving out more focused time for themselves.
I did poke around and asked engineers how the introduction of the Eng Metrics dashboard has changed the culture. I heard that most teams used the dashboard to debug issues – although there have been teams and groups where managers or directors set targets for the number of diffs per month (which metrics are met with ease: as you just create smaller diffs). A year after introducing the dashboard, the conversation seems to have moved on from here, and it is just another metric.
An interesting anecdote from Uber: after introducing the Eng Metrics dashboard: the lines of code did not change drastically, but the CI systems saw a visible increase in utilization. Basically, people started to create far, far more diffs, which put a much larger load on the continuous integration (CI) systems, and increased CI costs. So following measuring output, a behaviour change followed in more effort to improve these metrics measured.
The article wraps up with Part 2, where we cover the dangers of only measuring outcomes and impact; team vs individual performance; and answer how to measure developers. Read it here.
For other thoughts on developer productivity, see these past issues:
A new way to measure developer productivity – from the creators of DORA and SPACE
The full circle on developer productivity with Steve Yegge
Measuring software engineering productivity with Laura Tacho
Platform teams and developer productivity with Adam Rogal, director of developer platform at DoorDash
When I was learning photography, I heard a story about a photography teacher who divided his class into two groups: one group was graded on the quality of their best photos, and the other group was graded on how many photos the produced. At the end of the semester, the professor looked at which group produced the best work, and the pattern was clear: the majority of the highest quality photos came from the group asked to produce more work.
As an analogy, this is imperfect: new students are at a different point on the learning curve than professionals and likely benefit more from applying skills in new scenarios. But in my career, I've found that there's some truth there.
I'm a relatively new manager at a small company. I do my best to evaluate my team based on impact, but I also privately measure output, and there is an obvious correlation between the two. We're dealing with a novel product in an emerging market, and it's rarely clear which initiatives will be most impactful before we get prototypes into customer hands. It's unsurprising that the engineers on the team landing more changes have more hits and drive more customer acquisition and retention.
I conceptually believe that there are places where engineers are gaming output metrics and producing "busy work" with little value, but in my (admittedly limited) experience, I haven't seen much of that. I try to be aware of incentives; I don't tell the team I'm tracking output to avoid encouraging that type of work. Maybe this is the luxury of a small, process averse company.
I'm genuinely curious to hear from others who have experience in cultures where outcomes and impact don't track effort and output. As our company grows, I'll have some say in how engineers are evaluated, and I want to make sure we're being thoughtful.
One thing I always think about when reading about productivity is that "Productivity as a measurement is a good thing" seems to be a deeply ingrained and correct to folks, but I have to question how true it actually is. Let's take this particular measurement of productivity:
> For example, customer support can be measured by the number of tickets closed (an outcome), the time it takes to close a ticket (also an outcome,) and by customer satisfaction scores (impact.)
Most people agree that working customer support is a soul-crushing, terrible job, and that these metrics negatively impact their ability to service customers by incentivizing negative behaviours (copy/pasting answers without fully reading questions, closing difficult calls to prioritize easier ones, etc.) - while customer support services are generally good for C-Levels, I do wonder just how much better for customers and workers they would be if this fetish for measurement was put aside for a more holistic approach to outcomes and impact.
Unlikely, of course, and probably utopian ideal, but something I always find myself thinking about.